# Kitchen Renovation: The Order Trades Work In

> The usual order of trades in a kitchen refit: strip out, first fix, plaster, floor, units, worktops, second fix, tiling and decoration.

Last updated: 2026-11-14

The usual order of trades in a kitchen refit: strip out, first fix, plaster, floor, units, worktops, second fix, tiling and decoration.

Remodelers UK

Updated November 2026

5 min read

**In this guide**

Plan this room in 3D →

**Short answer:** A kitchen refit usually runs in this order: strip out, first-fix plumbing and electrics, plastering, flooring, units, worktops, second fix, splashback and decoration, over about 3 to 6 weeks on site. Getting the order wrong costs time and money, because each trade depends on the previous one.

## The sequence

| Step | Trade | Typical time |
|---|---|---|
| 1. Strip out old kitchen | Builder | 1 to 2 days |
| 2. First-fix electrics and plumbing | Electrician and plumber | 2 to 3 days |
| 3. Plaster and make good | Plasterer | 1 to 2 days plus drying |
| 4. Flooring | Fitter | 1 to 2 days |
| 5. Units and appliances | Kitchen fitter | 3 to 5 days |
| 6. Worktops (after templating) | Worktop fitter | 1 day plus 1 to 2 weeks lead time |
| 7. Second fix | Electrician and plumber | 1 to 2 days |
| 8. Splashback, decoration, snagging | Tiler and decorator | 2 to 4 days |

## Worktop lead time

Stone and quartz worktops are templated only once the units are fitted, then made in a factory. That is why the kitchen often sits for one to two weeks without a worktop. Plan a temporary arrangement.

## Who coordinates

Either you employ each trade separately, a main builder coordinates them, or the kitchen company supplies a fitter. Whichever you choose, agree who owns the programme in writing.

## Before the strip out

- Order units and appliances early.
- Confirm sockets, lights and water points on a plan.
- Check the cost range in our [kitchen cost guide](https://remodelers.uk/average-kitchen-renovation-cost-uk-2026/).

## Frequently asked questions

### How long does a kitchen fit take?

About 3 to 6 weeks on site for a full refit, plus lead time for the units.

### Should flooring go before units?

It depends on the kitchen and the supplier’s advice; confirm with your fitter before the floor is laid.

[Lay out your kitchen in 3D before ordering](https://remodelers.uk/studio/?from=%2Fblog%2Fkitchen-renovation-order-of-trades-uk%2F)

## Related guides

- [Kitchen worktop costs](https://remodelers.uk/blog/kitchen-worktop-costs-uk/)
- [Small kitchen layout planner](https://remodelers.uk/small-uk-kitchen-layout-planner/)
- [Kitchen renovation cost](https://remodelers.uk/average-kitchen-renovation-cost-uk-2026/)

This guide is general information for homes in the UK, not legal, structural or financial advice. Costs are indicative ranges and vary with your property, region, specification and builder; always obtain written quotes.

---