Short answer: In England a full plans application is checked and approved before work starts, while a building notice lets you start 48 hours after notifying Building Control but without prior approval. Full plans is safer for structural, extension and loft work; a building notice suits small, simple jobs.
The two routes compared
| Full plans | Building notice | |
|---|---|---|
| Drawings needed | Detailed drawings and calculations | Minimal at the start |
| Approval before starting | Yes, in 5 weeks (up to 2 months with agreement) | No, you can start 48 hours after notice |
| Risk | Lower: design approved first | Higher: Building Control may require changes later |
| Best for | Extensions, lofts, structural changes | Small alterations, minor works |
| Not available for | – | Some non-domestic buildings and certain complex cases |
Inspections you should expect
- Excavation and foundations before concrete.
- Damp-proof course and drains.
- Structure, beams and fire protection.
- Insulation and ventilation before closing up.
- Final inspection and a completion certificate.
Approved inspector or local authority
You can use the local authority or a registered Building Control approver. Either way, keep the final certificate with the house papers; buyers and solicitors ask for it.
If work was done without approval
You can apply for regularisation, a retrospective route, though it may mean opening up work for inspection. In some cases an indemnity policy is offered, but it is not the same as a certificate.
Frequently asked questions
How much does Building Control cost?
Fees vary by council and project value, from a few hundred to over a thousand pounds for a typical extension.
Do I need Building Regulations for a new kitchen?
Not usually for a like-for-like refit, but changes to electrics, drainage, ventilation or structure may.
Is this the same in Scotland?
No. Scotland uses building warrants issued by the local authority verifier.
Related guides
This guide is general information for homes in the UK, not legal, structural or financial advice. Costs are indicative ranges and vary with your property, region, specification and builder; always obtain written quotes.