Short answer: A single-storey house extension typically takes 6 to 15 months from first design to handover: 3 to 9 months for design, engineering, approvals and finding a builder, then 3 to 6 months on site. Double-storey projects add months, and delivery delays and weather can stretch both phases.
The typical timeline
| Stage | Typical duration |
|---|---|
| Brief, survey and design | 1 to 3 months |
| Planning or lawful development certificate | 2 to 3 months (8 weeks target for most householder applications) |
| Building Regulations drawings and engineer | 1 to 2 months (can overlap) |
| Tendering and choosing a builder | 1 to 2 months |
| Build | 3 to 6 months |
| Snagging and completion certificate | 2 to 4 weeks |
What delays projects
- Planning objections or requests for changes.
- Party wall notices and awards.
- Long lead times for steel, glazing and kitchens.
- Winter weather during groundworks and roofing.
How to save time
- Decide the layout and kitchen early.
- Order long-lead items as soon as drawings are approved.
- Choose the builder before the start date, not after.
Plan before you pay
A 3D plan lets you settle the layout, glazing and furniture before the drawings are finalised, which avoids redesign during the build.
Frequently asked questions
How long does planning permission take?
Householder applications are normally determined within 8 weeks, although some take longer.
Can I live in the house during the build?
Often yes for a rear extension, with kitchen disruption.