Short answer: A kitchen refit usually runs in this order: strip out, first-fix plumbing and electrics, plastering, flooring, units, worktops, second fix, splashback and decoration, over about 3 to 6 weeks on site. Getting the order wrong costs time and money, because each trade depends on the previous one.

The sequence

StepTradeTypical time
1. Strip out old kitchenBuilder1 to 2 days
2. First-fix electrics and plumbingElectrician and plumber2 to 3 days
3. Plaster and make goodPlasterer1 to 2 days plus drying
4. FlooringFitter1 to 2 days
5. Units and appliancesKitchen fitter3 to 5 days
6. Worktops (after templating)Worktop fitter1 day plus 1 to 2 weeks lead time
7. Second fixElectrician and plumber1 to 2 days
8. Splashback, decoration, snaggingTiler and decorator2 to 4 days

Worktop lead time

Stone and quartz worktops are templated only once the units are fitted, then made in a factory. That is why the kitchen often sits for one to two weeks without a worktop. Plan a temporary arrangement.

Who coordinates

Either you employ each trade separately, a main builder coordinates them, or the kitchen company supplies a fitter. Whichever you choose, agree who owns the programme in writing.

Before the strip out

  • Order units and appliances early.
  • Confirm sockets, lights and water points on a plan.
  • Check the cost range in our kitchen cost guide.

Frequently asked questions

How long does a kitchen fit take?

About 3 to 6 weeks on site for a full refit, plus lead time for the units.

Should flooring go before units?

It depends on the kitchen and the supplier’s advice; confirm with your fitter before the floor is laid.