Short answer: A kitchen refit usually runs in this order: strip out, first-fix plumbing and electrics, plastering, flooring, units, worktops, second fix, splashback and decoration, over about 3 to 6 weeks on site. Getting the order wrong costs time and money, because each trade depends on the previous one.
The sequence
| Step | Trade | Typical time |
|---|---|---|
| 1. Strip out old kitchen | Builder | 1 to 2 days |
| 2. First-fix electrics and plumbing | Electrician and plumber | 2 to 3 days |
| 3. Plaster and make good | Plasterer | 1 to 2 days plus drying |
| 4. Flooring | Fitter | 1 to 2 days |
| 5. Units and appliances | Kitchen fitter | 3 to 5 days |
| 6. Worktops (after templating) | Worktop fitter | 1 day plus 1 to 2 weeks lead time |
| 7. Second fix | Electrician and plumber | 1 to 2 days |
| 8. Splashback, decoration, snagging | Tiler and decorator | 2 to 4 days |
Worktop lead time
Stone and quartz worktops are templated only once the units are fitted, then made in a factory. That is why the kitchen often sits for one to two weeks without a worktop. Plan a temporary arrangement.
Who coordinates
Either you employ each trade separately, a main builder coordinates them, or the kitchen company supplies a fitter. Whichever you choose, agree who owns the programme in writing.
Before the strip out
- Order units and appliances early.
- Confirm sockets, lights and water points on a plan.
- Check the cost range in our kitchen cost guide.
Frequently asked questions
How long does a kitchen fit take?
About 3 to 6 weeks on site for a full refit, plus lead time for the units.
Should flooring go before units?
It depends on the kitchen and the supplier’s advice; confirm with your fitter before the floor is laid.