Short answer: A standard UK family bathroom refit takes about 7 to 15 working days on site: strip out, first-fix plumbing and electrics, boarding, waterproofing, tiling, fitting the suite and finishing, with grout and sealant curing times built in. Layout changes, wet rooms and delays in tile or suite delivery add days.

Typical schedule

DaysWork
1 to 2Strip out, protect floors, check for damp and pipework
2 to 4First-fix plumbing and electrics, extractor and any floor changes
4 to 6Boarding, waterproofing, floor levelling
6 to 10Tiling and grouting (curing time applies)
10 to 13Fit suite, shower, radiator, lighting
13 to 15Sealant, decoration, snagging

Basis: typical UK 2026 bathroom refit; a full cost range is in our bathroom cost guide.

Order and deliveries

Have the suite, tiles and shower on site before strip out. A missing tile can pause the job for weeks. Order a little extra tile for cuts and future repairs.

What needs approval

Replacing like for like rarely needs Building Regulations approval, but new circuits, extractors or drainage changes may. Waterproofing and electrical zones matter for safety: see our wet room guide.

Planning without a bathroom

  • Arrange another washing and toilet option.
  • Agree working hours and noise.
  • Keep access to a stop tap.

Frequently asked questions

How long without a bathroom?

Usually 1 to 3 weeks; in a one-bathroom home plan access to a neighbour, gym or temporary arrangement.

Can I stay in the house?

Often yes, but expect dust and no water at times.

Try bathroom layouts in 3D first

This guide is general information for homes in the UK, not legal, structural or financial advice. Costs are indicative ranges and vary with your property, region, specification and builder; always obtain written quotes.